It depends upon type and importance of the structure and nature of soil strata. The cost involved should be in mind while planning the program. The following information is to get by conducting the exploration, the depth, thickness, extent and composition of each strata, depth of rock, and depth of ground water table. We must sought strength and compressibility of the strata for to make an estimate of safety and expected settlement of the structure. A site plan should be prepared. A layout plan of proposed building with column locations an its expected loads. Location of bore holes is decided along with other field tests. A careful planning is needed for the boring program. Trained persons in geology and geotechnical engineering is necessary.
Two important aspects of a boring program
are spacing and depth of boring.
Spacing of Borings
The spacing and number of borings are
related to the type, size, and loads of proposed structure. It is also depends
on condition of soil horizontally and vertically. The local building code will
be useful.
|
S. No |
Nature of the Project |
Spacing of Borings in meters |
|
1 |
Highway (subgrade survey) |
400 |
|
2 |
Earth dam |
40 |
|
3 |
Borrow Pits |
70 |
|
4 |
Buildings |
20 |
|
5 |
Single Storey Buildings |
50 |
The conditions of soil that is its
uniformity is a factor for the spacing. IS1892, 1979 will be recommended for
reference.
Depth of Borings
In order to get adequate information to
predict the settlement of the structure, the boring should be deep enough to
loading influence zone of the soil strata. The boring shall be gone up to the
rock for huge buildings and bridges. For small buildings 15 or 20 meters is
sufficient.
Previous loading history is known for
settlement study. According to IS 1892, 1979 the depth of exploration required
depends up on the type of the structure, its total weight, the size, shape and
disposition of the loaded area, soil profile and the physical properties of the
soil that constitutes each stratum.
Boring Log
The record of the information got from borings is called boring log.
Depth of borings IS 1892 1979
|
S. No |
Type of Foundation |
Depth of Boring |
|
1 |
Isolated
spread footings or Raft |
1.5
times the width |
|
2 |
Adjacent
footings spacing less than twice width
|
1.5
times the width |
|
3 |
Pile
and well foundations |
1.5
times the width of the structure from bearing level |
|
4 |
Road
cuts |
equal
to bottom width of the cut |
|
5 |
Fill |
2
meters below the ground level or equal to the height of fill which is great |
Soil Sampling
It is the process of obtaining samples of soil from the desired depth at the desired location from a natural soil
deposit, for laboratory examination to assess its properties. From different
stratas samples are taken. Determination of GW level is also a sampling.
There are disturbed and undisturbed
samples, which is to be tested in the laboratory. The samples taken may loss
its physical properties for example compaction. A fully undisturbed sample can
not be taken.